Installing Noodoe EV's

AC7L/AC7LC EV CHARGER

Going from shipment to operational takes only three steps. Install the charger. Activate it. Subscribe to Noodoe EV OS using the site owner’s credentials (required for operation).

HOW TO INSTALL YOUR AC7L/AC7LC CHARGER

Run through the pre-installation checklist

Make sure you have everything in the box

Read the Installation Guide and get everything mounted

Set up internet connection

Power up your charger!

What's In The Box

Tools for Installation
Mounting Bracket194x109x9 mm
Model Accessories
Holster ASSY58x58x70 mm
Model Accessories
ScrewsTapping: #12 & Mechanical: M6
Model Accessories
Wire, Copper
(AC7LC Only)
8 AWG
Commercially Available
Heat Shrink Tube
(AC7LC Only)
For 8 AWG wire
Commercially Available
Terminal
(AC7LC Only)
For 8 AWG wire
Commercially Available
Conduit
(AC7LC Only)
1 inch
Commercially Available
Torx ScrewdriverT20
Philips ScrewdriverPH3
Hexagon Socket5/16

Pre-Installation Checklist

Check for damages incurred during transportation.
Before connecting the product to the power supply, check that the power supply voltage and current ratings correspond with the power supply details shown on the product rating label.
CAUTION: Disconnect the power supply before installing or repairing the charge point. Failure to do so may result in physical injury or damage to the power supply system and the charge point.
The charge point must be installed only by a licensed electrician in accordance with the provisions of the local electrical industry construction standards and should comply with national electrical codes and standards.
Sufficient space is necessary for product installation and maintenance; please keep not less than 107cm clearance distance from all around the product.
Before installing the charge point, make sure you have read all instructions in the user’s manual and fully understand its contents.
Appropriate protection is required when connecting to a main switchboard.

installation

Follow the instructions in the User’s Guide to complete the installation of the EV charging stations.

User's Guide

Set up internet connection

NOTE: Noodoe EV charging stations require internet connectivity to complete charger activation and to provide charging services. 

The charging station comes with a standard RJ45 connector. You can choose to connect the charger to a wired internet connection at the site or to a switch that is connected to a 4G router

If An Internet Connection Exists

Connecting your charger to the internet is easy if you already have a wired internet connection.

OR

If An Internet Connection Is Not Available

You have to establish a connection via a 4G router. If you're installing multiple chargers at a given site you may use an internet switch to extend Internet connectivity for multiple chargers:

IMPORTANT: A high-quality commercial-grade 4G router is required for stable operation of the charging stations.

A consumer router will freeze after a few months and require a reset. Commercial-grade routers are designed for years of continuous operation under harsh conditions. Additionally, they can auto-reboot should the routers stop working. This ensures dependable, automated service. Please contact your Noodoe EV representative or distributor if you require help with obtaining a commercial-quality Noodoe-certified 4G router.

Additional Internet Considerations:

  1. Confirm that the end to end ping response is less than 100ms.
  2. Confirm that the signal strength at the installation point indicates full strength or close to it. Make sure that you monthly data quota is at least 2GB. 
  3. Place the 4G router in a location where it does not experience any interference or where signal is blocked.
  4. Avoid intermingling power lines with network lines to eliminate chance of interference.
  5. Make sure to use cables that are Cat5e or above with a maximum length of less than 100m or a switch should be deployed.
  6. Dedicated AP (access points are required). Do not exceed more than 2 APs.
  7. The following ports must be opened by firewall in order for the charging station to communicate: 22, 8998, 16000. 

Powering On

After all the electrical work has been completed and an internet connection has been established, you can power up the charging station. Open up the side cover with a T8 Torx screwdriver and turn the breaker to the ON position.

Continue to Activation